- Construction of new Restrooms for Skate Park and Splashpad: The design layout of the building is complete and approved by the city. The site plan and sewer pumping station is being performed in-house by the Engineering department and will be completed with the final architecture plans. We expect to submit for permitting in mid-September and put out to bid by the end of September 2026.
- Seven-Mile Marina Building Re-Development: We are holding off on bidding this project until we have wrapped up other ongoing projects. The project will renovate the existing building to provide for the permanent reception for Pigeon Key, along with an office for Marina personnel use. We will also have an additional area for lease within the building. In addition to the mentioned uses, we will also provide an area for enclosed lockers for use by the charter boat captains.
- 92nd Street road being raised: We anticipate coordinating a meeting to inform the residents of the proposed design and impacts due to the road being raised. We are still pursuing funding for he construction phase of the project. the project design and permitting should be completed by the end of 2026.
- Sombrero Beach Road bike path improvements: Our consultant is proceeding with the design. Prior to submittal to FDOT, the City will host a community outreach meeting so that residence can be informed of the upcoming project, and our consultant ca address any reasonable input from the public. We anticipate construction to begin in late summer of 2027.
- Aviation Blvd. Trail lighting project: Our consultant has submitted the 100% plans to FDOT for approval. Once approved by FDOT, the project will be ready to go out to id in the summer of 2027, which begins FDOT's 2028 fiscal year. The project construction is funded by a $959,400 grant from FDOT. The project is slated for construction in the summer of 2027.
- Coco Plum Trail lighting project: Staff have completed our negotiations with McFarland-Johnson for the design of trail lighting from US 1 to Ave. K. The construction of this project is funded by FDOT under the LAP program in an amount of $1,000,000. We expect design to begin in October 2026 and will go through the review process with FDOT. Construction is scheduled for the fall of 2027.